July 4th, 2015

Engineering News July 2015

Harco Engineering continues to machine the cylinder block halves. Kevin West (West Steam Design) has completed CAD plotting the frame plates and they are to be dispatched for shot blasting and machining after a meeting with Bob Meanley to discus and agree a schedule. West Steam Design has completed the design of the horn guides and CAD design of the motion bracket is pending. The machined cylinder block halves, diamond stay and tank supports are to return to Tyseley ahead of the assembly of GER 789’s frames.